Lining and materials7 min

Relining a low-pressure die casting furnace: best practice

When the old lining of a low-pressure die casting furnace no longer holds, patching will not help. This article shows how a complete relining in the workshop proceeds, from break-out through cast walls, insulation and floor to lid and heat-up curve, and how to recognise good workmanship.

Bath chamber of a low-pressure die casting furnace seen from above after relining: cast walls with openings, surrounded by a ring of insulating firebricks

A low-pressure die casting furnace is not a melting furnace with a lid, but a closed furnace that works with gas pressure. A slight gas overpressure above the aluminium bath pushes the melt from below through the riser tube into the die. The refractory lining therefore has to do two things: withstand the melt and be part of a tight system. As long as it is worn only in individual places, a repair is often enough. But when the old lining has broken out in many places, aluminium has penetrated the wall and nobody can say any more what is still sound behind it, the only option left is a complete relining.

The procedure below is based on two low-pressure die casting furnaces that SBS Refractory Service overhauled in 2026: a general overhaul in the summer and a complete relining in November, for two different customers. It describes what has proven itself, and where most mistakes are made.

1. Assess the condition honestly

The first question is whether patching still makes sense. Three findings in particular speak against a partial repair: aluminium has penetrated deep into the working layer or right into the insulation, cracks run through the entire wall, or the insulation behind it has become crumbly and damp. In all three cases, new material would sit on a substrate that no longer holds. With a furnace that operates under pressure, there is a further point: every joint between old and new is a possible path for melt and gas.

View through the encrusted charging opening into the broken-out old brick lining of a low-pressure die casting furnace
Starting point for the complete relining in November: old lining broken out in many places

2. Break out down to the steel and inspect the casing

A complete relining starts with breaking out the lining entirely, down to the steel casing. Only then can the casing be assessed: is it distorted, are flanges and sealing faces flat, are welds cracked, has pitting corrosion formed? Anything overlooked here will later show up as a leak that the refractory lining cannot compensate for. The casing is cleaned and damage to the steel structure is repaired before the first layer is installed.

3. Install the insulation correctly first

Behind the working layer lies the insulation; in the November project, insulating firebricks were used for it over the full wall height. It determines how much energy the furnace consumes in holding operation and how hot the casing becomes. The bricks are laid tightly butted with staggered joints, either dry or with a thin mortar joint depending on the system, so that no continuous thermal bridge is created. In the melt zone, the insulation must be completely covered by the working layer: insulating firebricks are light and porous and cannot withstand liquid aluminium.

4. Cast the bath chamber instead of bricking it

The monolithic construction method has proven itself for the walls of the bath chamber. The chamber is round and has openings and a charging opening; bricked, this would create many joints and cut-to-fit pieces, which are exactly the spots where aluminium attacks first. Casting is done in dimensionally accurate formwork, with the openings left out at the same time. In contact with the melt, materials should be used that are poorly wetted by aluminium and thus counteract infiltration and corundum formation.

  • Measure the mixing water, do not add it by feel: even a little water above the manufacturer's specification makes the castable more porous and weaker.
  • Cast in one go and compact thoroughly so that no cold joints or voids form.
  • Only strip the formwork after the setting time specified by the manufacturer, and keep an eye on the temperature during setting.
  • After stripping, measure and document the wall thicknesses and the dimensions of the openings.

For low-pressure and dosing furnaces, manufacturers also offer linings made of pre-fired precast shapes. Their advantage is the short drying time, because most of the water has already been driven out at the factory. On the other hand, a precast build-up has butt joints that have to be backfilled and sealed, and it only fits furnace bodies with known dimensions. For an older furnace with its own openings and a distorted casing, casting in formwork is usually the more adaptable solution, provided drying and heat-up are taken seriously.

View through the charging opening of a low-pressure die casting furnace onto the cast wall with openings and the new floor
Cast wall with openings left out, below it the new floor

5. The floor: two-component castable

The floor carries the load of the bath, and it is scraped during cleaning. In the November project, it was cast with a special two-component castable. With such systems, the two components are supplied separately and only mixed immediately before installation. The mixing ratio is fixed and the working time is limited. That is why it is planned in advance how much can be installed in what time, and the material is only mixed once the substrate and tools are ready.

6. Lid, penetrations and sealing faces

In the end, the furnace has to close tightly again. The lid, penetrations and sealing faces are refurbished, and the riser tube seat is made dimensionally accurate and tight. The riser tube is one of the most heavily loaded components of the furnace, and any leak at the lid disturbs the pressure control and thus the mould filling. This work is part of the relining, even though it is not refractory work in the narrower sense. Before commissioning, the tightness of the closed furnace body must be tested and the result recorded, because tightness cannot be judged by eye. Who carries out the test is agreed beforehand; in the November project, the customer tested it itself.

Refurbished lid with penetrations on a relined low-pressure die casting furnace
Lid with penetrations after refurbishment

7. Dry-out and heat-up according to a curve

Freshly cast refractory castable contains water that has to come out during the first heat-up. If this happens too quickly, steam pressure builds up in the structure and the lining can spall. The initial heat-up therefore follows a curve with holding stages that depends on the materials used and the wall thickness. It is agreed with the operator and belongs in the furnace documentation, as do materials, batches and dimensions.

The most important decision is made at the start: a complete relining pays off when it is done consistently. Breaking out completely, inspecting the casing and casting the bath chamber without brick joints gives you a furnace whose condition you know, instead of a patchwork whose weak points only show up in operation.

How to recognise a good relining

  • The break-out goes down to the steel, and the casing is inspected before relining.
  • In the melt zone, the insulation is completely covered by the working layer, and its joints are staggered.
  • The bath chamber is cast without brick joints, and openings are left out rather than drilled afterwards.
  • The materials chosen for the floor and for contact with the melt suit the load.
  • Lid, sealing faces and riser tube seat are part of the order, and it is clear who tests tightness before commissioning.
  • There is a heat-up curve and documentation with materials, dimensions and photos.
At a glance
Closed system
The lining is part of a tight furnace, not just heat protection
Down to the steel
break-out when the old lining no longer holds
No brick joints
cast bath chamber instead of bricked cut-to-fit pieces

Practice sheets on this topic

Technical newsletter

Get new practice sheets automatically

All PDFs on this page are free, without sign-up. If you want to know when a new sheet is added: one e-mail a month, unsubscribe anytime.

Running heat-up curves correctly
PDFAll furnace types

Running heat-up curves correctly

Why the first days decide over years of service life.

Only in the PDFExample curves for ramming mix, castable and brick lining with hold points and ramp rates
To the article
Repair or reline? The three findings
PDFAll furnace types

Repair or reline? The three findings

When a targeted repair is enough, and the three findings where only a relining will hold.

Only in the PDFDecision table with 6 findings, the 3 typical wrong decisions, 2 photos from a relining
To the article
Refractory on the tube wall: The inspection points
PDFEnergy & Combustion

Refractory on the tube wall: The inspection points

Protecting without blocking the heat: what matters when lining a boiler tube wall.

Only in the PDF7-point checklist for tube walls, the 3 typical mistakes, 2 photos from the boiler
To the article

More insights from our projects

New insights from the job site every week – damage patterns, relinings and practical refractory know-how.

Share this article on LinkedIn

Exactly your question?

Then let's talk about your furnace: inspection, lining or maintenance during operation. Free initial consultation, quick reply.

CallSend enquiry

Your privacy matters to us.

We use cookies and similar technologies to ensure that our website functions properly and to analyse how our content is used. In the settings you can choose which cookies you wish to allow. Privacy policy