Lining and materials6 min

Refractory castable in winter: cold, frost and setting

Many overhauls fall in the cold season, and refractory castable is sensitive to temperature. Below about 10 °C it sets more slowly, below 5 °C setting can stall, and if it freezes before drying it loses a considerable amount of strength. What has to stay warm before, during and after casting, and how to plan for it.

Empty furnace chamber in a hall under a tarpaulin roof: exposed, rust-tinged steel shell with rows of anchors, yellow formwork for the castable on the floor

Overhauls are scheduled when production allows, and that is often in winter: the Christmas shutdown, the turn of the year, the quiet weeks in January. Cement-bonded refractory castable is a hydraulically setting material: it needs water and warmth for the cement to react, and it is unforgiving of cold. The consequences often only become visible during heat-up, when the lining spalls although material and installation appeared to be in order.

Why cold slows castable down

Most castables are bonded with high-alumina cement (calcium aluminate cement). How quickly it reacts, and which hydrates it forms, depends strongly on temperature. In the cold, hydration runs more slowly, setting is delayed and the formwork can only be stripped later. The colder it is, the more of the hydrate CAH10 forms. It binds a great deal of water, is less dense and later converts into denser phases, releasing water and leaving the structure more porous. This water has to come out again during drying. Manufacturers point out that a lining that has set in the cold is more prone to spalling during heat-up.

Manufacturers' installation guidelines differ in detail, but they all point the same way: material, mixing water and mix should ideally be between about 10 and 25 °C. Many guidelines give 5 °C as the lower limit for material and water; some also require at least 10 °C for the surroundings and the steel shell. For gunning mixes used with an accelerator, the lower limit applies to the accelerator as well. The data sheet of the product used is always decisive; where it is stricter than a general rule, the data sheet applies.

Frost before drying: the most expensive mistake

Cool means slow; frozen means damaged. As long as the castable has not dried, there is free water in its pores. If that water freezes, it expands and loosens the young structure. Strength drops considerably, and the surface gives no sign of it. During the later heat-up, the same weakened structure has to withstand the steam pressure. Manufacturers therefore all specify that the lining must not freeze during installation and setting, and that it must remain frost-free until drying begins. Anyone planning a pause of a few days between casting and heat-up, over the holidays for example, has to heat the furnace on those days too.

Frost protection applies not just to the first few hours but until drying begins. A furnace left standing cold over the weekend after casting is just as much at risk during that time as on the day of casting.

What has to be warm before casting

  • The dry material: bagged material that has stood in a cold store or on a lorry takes a long time to warm through. Manufacturers recommend storing it dry and frost-free and placing cold pallets in a heated room several days before installation (one guideline specifies at least 72 hours), with the bags spread out so that warm air can circulate. Measure the temperature inside the bag; do not guess it.
  • The mixing water: in winter, tap water is often only a few degrees above freezing. Warmed water brings the mix into the right range. It must not be too hot, though: above about 25 °C setting accelerates markedly, and the mix can stiffen in the mixer or the pump.
  • The steel shell and the anchors: cold plate draws heat out of the fresh mix at the contact surface. The furnace chamber should be heated and brought up to temperature before casting, not only afterwards.
  • The amount of water: cold castable feels stiffer, and the temptation to add more water is strong. Every litre above the data sheet specification lowers the strength, prolongs setting and is extra water that has to escape as steam during heat-up.
Yellow timber formwork in a furnace opening, next to it the freshly cast, light-coloured castable wall, in front a folding rule for checking the wall thickness
Formwork at the opening of a chip melting furnace: in winter, how early it can be struck depends on the temperature in the furnace chamber, not on the clock.

Enclose and heat

With outside temperatures close to or below freezing, there is no way round an enclosure: the furnace chamber closed off, openings sealed with tarpaulins or insulating mats and, if necessary, a tent outside around the mixing area and access. Heating runs continuously through installation and setting until drying. Position heaters so that they warm the air in the chamber rather than blowing directly onto the fresh surface. Otherwise the skin dries too quickly while the interior is still cold.

The mixing area and the furnace are often at different points in the hall. On the way, the mix cools down, especially with long delivery lines or when skips are carried through an open door. Set up the mixing area as close as possible and inside the heated zone.

Setting, stripping, heat-up

  • Setting times in the data sheet apply at normal temperature. At 10 °C, hardening can take considerably longer; base stripping times and the start of heat-up on the actual condition of the castable, not on the construction schedule.
  • Measure and record the temperature of the air, shell and lining throughout the setting period. These values belong in the furnace records and, if damage occurs later, are the only reliable evidence.
  • The heat-up curve only begins once the castable has set. A lining that has set in the cold contains more bound water; holding times at the critical temperatures must not be shortened to make up for lost days.
  • If drying is postponed, keep the furnace closed and above 10 °C so that neither frost nor moisture can get in from outside.
Measuring instrument on a tripod in front of an open furnace door, thermocouple cables leading into the furnace chamber, from which steam is rising
Drying with measurement: the steam shows how much water a fresh lining contains. After setting in the cold, there tends to be more.

What belongs in the planning of a winter overhaul

  • Clarify early on whether the furnace chamber and the mixing area can be heated, and who provides heaters, fuel or power.
  • Schedule delivery of the castable so that it can stand in a warm room for several days before installation, and plan that room in.
  • Allow buffer time for longer setting instead of clawing it back during heat-up.
  • Decide who monitors the heating overnight, at weekends and on public holidays.
  • Prefabricate parts where possible: precast shapes cast in a heated workshop avoid the cold problem at the plant.

Cold can be planned for. A tent, two heaters and a thermometer cost a fraction of a lining that spalls at the first heat-up. What matters is that the heat is in the schedule and the budget before the first bag is opened.

At a glance
≥ 5 °C
usual manufacturer lower limit for dry material and mixing water; some also require 10 °C for the surroundings and the steel shell
10–25 °C
target range for the finished mix: colder sets too slowly, warmer too quickly
frost-free
from installation until drying begins, not just in the first few hours after casting

Practice sheets on this topic

Technical newsletter

Get new practice sheets automatically

All PDFs on this page are free, without sign-up. If you want to know when a new sheet is added: one e-mail a month, unsubscribe anytime.

Running heat-up curves correctly
PDFAll furnace types

Running heat-up curves correctly

Why the first days decide over years of service life.

Only in the PDFExample curves for ramming mix, castable and brick lining with hold points and ramp rates
To the article
Repair or reline? The three findings
PDFAll furnace types

Repair or reline? The three findings

When a targeted repair is enough, and the three findings where only a relining will hold.

Only in the PDFDecision table with 6 findings, the 3 typical wrong decisions, 2 photos from a relining
To the article
Refractory on the tube wall: The inspection points
PDFEnergy & Combustion

Refractory on the tube wall: The inspection points

Protecting without blocking the heat: what matters when lining a boiler tube wall.

Only in the PDF7-point checklist for tube walls, the 3 typical mistakes, 2 photos from the boiler
To the article

More insights from our projects

New insights from the job site every week – damage patterns, relinings and practical refractory know-how.

Share this article on LinkedIn

Exactly your question?

Then let's talk about your furnace: inspection, lining or maintenance during operation. Free initial consultation, quick reply.

CallSend enquiry

Your privacy matters to us.

We use cookies and similar technologies to ensure that our website functions properly and to analyse how our content is used. In the settings you can choose which cookies you wish to allow. Privacy policy