Demolition work on a cupola furnace near Tuttlingen

Cupola furnace demolition in record time – safe preparation for the relining

Furnace type:Cupola furnace
Location:Tuttlingen area
Service:Complete demolition of the old lining
Industry:Foundry industry
Project overview

Initial situation

A foundry near Tuttlingen was planning to reline its cupola furnace. This required the complete and professional demolition of the existing old lining. SBS Refractory Service was commissioned with the demolition work – a demanding task given the confined conditions at the furnace.

Scope of services

  • Deployment planning and safety preparation
  • Complete demolition of the old lining
  • Removal and proper disposal of the demolition material
  • Inspection and cleaning of the furnace structure
  • Handover for the subsequent relining

Project data

Furnace typeCupola furnace
LocationTuttlingen area
ServiceComplete demolition of the old lining
IndustryFoundry industry
Challenges

The task

The cupola furnace offered only limited access for the demolition work

The old lining had to be removed without residue and without damaging the load-bearing furnace structure

Suitable equipment and experienced personnel were required for the confined conditions

The work had to be completed safely and on schedule to keep to the timetable for the relining

Our solution

The SBS approach

Our team prepared the assignment carefully and was on site with the right equipment. The demolition work was carried out systematically and in strict compliance with all safety requirements.

Despite the confined conditions at the cupola furnace, the team worked efficiently and in a coordinated manner. The old lining was removed completely and without residue, leaving the furnace structure undamaged.

The demolition was completed on schedule and the furnace was handed over prepared for the subsequent relining.

Project impressions

Demolition work on a cupola furnace near Tuttlingen in pictures

Demolition work on the cupola furnace near Tuttlingen
01

Systematic demolition of the old lining under confined conditions

Close-up of the demolition work on the cupola furnace
02

Precise working methods for residue-free results

Fully prepared cupola furnace after demolition
03

Cleanly prepared furnace – ready for the relining

Results

Measurable results

The key figures of the “Demolition work on a cupola furnace near Tuttlingen” project

On schedule
Completed within the planned time window
Safe
Entire demolition without safety incidents
Residue-free
Clean preparation for the relining
Coordinated
Efficient working under confined conditions