Project overview

Initial situation

A foundry with two works in Baden-Württemberg runs its melting and crucible furnaces all year round. They only go cold in the week between Christmas and New Year. From 2020 to 2023, SBS used that week four years in a row: overhauls, cleaning, maintenance gunning and repairs on crucible furnaces, melting furnaces and a transport ladle — fifteen deployments across both works.

Scope of services

  • Crucible furnace
  • Overhaul
  • Maintenance gunning
  • Transport ladle
  • Shutdown planning

Project data

UnitsCrucible furnaces, melting furnaces, transport ladle
ServiceOverhaul, cleaning, maintenance gunning, repair
Period2020 to 2023, fifteen deployments
LocationsTwo works of a foundry in Baden-Württemberg
Crew1 to 4 fitters per deployment
Challenges

The task

The window is the holiday week. There is no alternative date on which the furnace would otherwise stand cold

Two works, the same shutdown week — the order of play decides whether both get finished

Between the years nobody else is working: no supplier delivers, no workshop is open. Whatever is missing stays missing

Working over Christmas needs people who will carry it — and planning that does not make it a fresh surprise every year

Our solution

The SBS approach

The holiday week was planned in as fixed, not renegotiated each year. In four consecutive years the crew was in the works between 23 and 30 December.

Material and equipment went out before the holiday. Nothing is delivered between the years — what is not on site is not there.

The smaller jobs — cleaning, maintenance gunning, joints — ran in the same weeks. So the furnace is not merely repaired but cared for when it fires up again.

The units changed over the years, the core of the crew did not. Both works knew the people by first name, and on 27 December that saves every discussion.

Results

Measurable results

The key figures of the “Overhaul in the week between the years” project

4 years
in a row in the week between the years
15
deployments across both works, 2020 to 2023
2
works served in the same shutdown week
23–30 Dec
the window that does not otherwise exist

Planning a project?

Whether complete relining, repair or emergency — free initial consultation and a fast response.