SBS Refractory Service

Seven deployments at one iron foundry

Someone who knows the plant needs no briefing

Units:Induction furnaces at an iron foundry
Service:Inductor change, repair, ongoing refractory work
Period:January 2023 to January 2026, seven deployments
Crew:Usually 1 fitter, once 2
Awarded:Through a refractory materials supplier
Project overview

Initial situation

An iron foundry in the Upper Palatinate awards its refractory work through a materials supplier. Since January 2023 the fitters have come from SBS. By January 2026 it had become seven deployments: two inductor changes, plus repairs and ongoing refractory work. On six of the seven occasions, one single man travelled out.

Scope of services

  • Inductor change
  • Induction furnace
  • Refractory repair
  • Repeat customer
  • Effort-based billing

Project data

UnitsInduction furnaces at an iron foundry
ServiceInductor change, repair, ongoing refractory work
PeriodJanuary 2023 to January 2026, seven deployments
CrewUsually 1 fitter, once 2
AwardedThrough a refractory materials supplier
Challenges

The task

An inductor change is not a date you postpone: the furnace is down and the foundry is waiting for it

The deployments are small — one to four days. Send a new crew each time and half of it goes on briefing

The order comes through a supplier, the work happens at the foundry. Two parties have to be satisfied, and only one of them is standing next to you at the furnace

Small, recurring jobs only pay off if travel out and back does not eat the margin

Our solution

The SBS approach

The same crew across three years. Someone who has seen the furnace open five times knows where the lining tends to open up — and starts there.

Six of the seven deployments ran with one fitter. That only works if the preparation is right and nobody on site still has to explain what is needed.

Billing was almost entirely by effort. At this size, negotiating a fixed price costs more than it brings in.

The commercial line runs through the supplier, the agreement at the furnace runs directly. Both in parallel, without either side having to ask twice.

Results

Measurable results

The key figures of the “Seven deployments at one iron foundry” project

7
deployments at the same foundry since January 2023
6 of 7
deployments with just one fitter
2
inductor changes
3 years
the same crew throughout

Planning a project?

Whether complete relining, repair or emergency — free initial consultation and a fast response.

CallSend enquiry

Your privacy matters to us.

We use cookies and similar technologies to ensure that our website functions properly and to analyse how our content is used. In the settings you can choose which cookies you wish to allow. Privacy policy