Maintenance of an 18 MW wood combustion plant

18 MW plant maintained and optimised preventively

Plant type:Wood combustion plant, 18 MW
Service:Preventive maintenance and partial repair
Work:Cleaning, section renewal, arch rings, maintenance gunning
Industry:Renewable energy / biomass
Project overview

Initial situation

SBS Refractory Service was commissioned to carry out extensive preventive maintenance work on an 18 MW wood combustion plant. The plant generates heat and electricity from wood fuels and is run in continuous operation. The routine shutdown covered the complete inspection and overhaul of the refractory lining in order to ensure operational reliability and efficiency for the coming operating period.

Scope of services

  • Thorough cleaning of the entire furnace and gas duct
  • Inspection and condition assessment of all refractory-lined areas
  • Renewal of 6–8 worn sections of the lining
  • Replacement of 12 rings on the intermediate arch
  • Full-surface maintenance gunning as additional wear protection
  • Acceptance and release for the return to service

Project data

Plant typeWood combustion plant, 18 MW
ServicePreventive maintenance and partial repair
WorkCleaning, section renewal, arch rings, maintenance gunning
IndustryRenewable energy / biomass
Challenges

The task

The 18 MW plant required a systematic survey of all refractory-lined areas including the gas duct

Several sections of the lining showed advanced wear and had to be renewed within the limited shutdown period

The intermediate arch required repair at 12 rings – work that demands the utmost care during dismantling and reassembly

All work had to be completed within the planned shutdown window so as not to delay the restart of operations

Our solution

The SBS approach

Maintenance began with a thorough cleaning of the entire furnace including the gas duct. All deposits and residues from the combustion process were removed so that the condition of the lining could be assessed precisely.

Based on the inspection, 6 to 8 sections of the lining were identified as requiring renewal and were professionally replaced. On the intermediate arch, 12 rings were renewed, being carefully dismantled and rebuilt to size with new bricks.

Finally, the entire refractory lining received maintenance gunning, which acts as an additional protective layer, extending the service life of the lining and reducing wear in the coming operating period.

Project impressions

Maintenance of an 18 MW wood combustion plant in pictures

Interior of an 18 MW wood combustion plant during maintenance work by SBS Refractory Service
01

Maintenance work inside the 18 MW wood combustion plant

Refractory lining after renewal of the sections and maintenance gunning
02

Renewed brickwork with final maintenance gunning

Results

Measurable results

The key figures of the “Maintenance of an 18 MW wood combustion plant” project

18 MW
Plant output fully assured after maintenance
6–8 sections
Worn lining areas renewed
12 rings
Professionally replaced on the intermediate arch
Extended
Service life thanks to final maintenance gunning