SBS Refractory Service

Zone-Correct Relining of a Biomass Combustion Chamber

Three zones, three demands — the right material in every place

Plant type:Biomass CHP plant with moving-grate furnace
Service:Relining of the combustion chamber
Scope:Brickwork, monolithic zones, expansion joints, secondary-air nozzles
Industry:Power generation
Project overview

Initial situation

In the combustion chamber of a biomass CHP plant with a moving-grate furnace, the lining had reached the end of its service life: the fuel bed had ground down the brickwork above the grate, transitions and expansion joints were worn, and the structure around the secondary-air nozzles was damaged. The operator commissioned SBS Refractory Service with a zone-correct relining within the planned outage.

Scope of services

  • Survey of findings and measurement of the nozzle positions
  • Demolition of the worn lining
  • Brickwork above the grate, monolithic lining above it
  • Stepped interlocking transition, expansion joints packed with ceramic fibre
  • Handover with a written heat-up curve

Project data

Plant typeBiomass CHP plant with moving-grate furnace
ServiceRelining of the combustion chamber
ScopeBrickwork, monolithic zones, expansion joints, secondary-air nozzles
IndustryPower generation
Challenges

The task

Three completely different demands in one space: mechanical abrasion above the grate, peak temperature and turbulence in the secondary-air zone, alkali attack at the boiler inlet

The transition between brickwork and monolithic lining must not form a continuous weak point

The position of the secondary-air nozzles had to be preserved exactly — it is part of the combustion design and determines burnout

A tight outage window: demolition, rebuild and controlled heat-up within the planned period

Our solution

The SBS approach

Above the grate, a tight stretcher bond of fired firebrick was laid — with narrow joints where the fuel bed rubs against the wall with every stroke. Above it follows the monolithic lining, which forms corners, slopes and penetrations seamlessly in one pour.

The boundary between the two constructions was interlocked in steps, each step offset from the next — a crack that follows one step ends at the next. The expansion joints run vertically throughout and were packed with ceramic fibre instead of being filled with mortar. The secondary-air nozzles were surveyed before demolition and restored to the millimetre during installation.

At the boiler inlet, where the flue gases cool and the alkalis condense, a high-alumina material was used. Handover included a written heat-up curve so the mixing water of the monolithic zones can escape in a controlled way.

Project impressions

Zone-Correct Relining of a Biomass Combustion Chamber in pictures

Stepped interlocking transition between brickwork and monolithic lining
01

The boundary runs in steps, not straight — on the right, the continuous expansion joint

New firebrick bond directly above the grate bars
02

A tight stretcher bond with narrow joints where the fuel bed rubs against the wall

Newly built firebrick vault above the monolithically lined walls
03

The vault back in brick: arch bricks in bond, below them the seamless monolithic wall

Four secondary-air openings set during installation in the new wall section
04

Set during installation and restored to the millimetre — not drilled afterwards

Monolithic lining at the transition to the boiler
05

At the boiler inlet the alkalis deposit — high-alumina material stands here

Results

Measurable results

The key figures of the “Zone-Correct Relining of a Biomass Combustion Chamber” project

Zone-correct
Material chosen in every place for the strongest demand there
Interlocked
Brick/monolithic transition without a continuous weak point
To the millimetre
Secondary-air nozzles surveyed and restored
Documented
Handover with a written heat-up curve

Planning a project?

Whether complete relining, repair or emergency — free initial consultation and a fast response.